Council attempts to tackle the many unknowns of Vancouver’s looming AI data centres
As the next round of significant dates for Vancouver’s AI data centres approaches, the City continues to grapple with several key unknowns.
Whether both the Westbank AI data centres proposed for 150 West Georgia St. and 111 East 5th Ave. will proceed as planned, when they may be constructed, and what tools the City may have to address concerns raised by advocates remain uncertain.
Last week, OneCity Coun. Lucy Maloney introduced a motion to try to address some of these lingering questions.
The motion asked staff to develop a framework to monitor environmental and employment impacts of these proposed centres, including requiring applicants (prior to rezoning) to commission third-party assessments.
Among other considerations, the motion also asked staff to review whether the noise control bylaw adequately addresses “continuous mechanical noise” and how council might secure public benefit from bulk data storage infrastructure.
The motion, the successor to a similar motion introduced by Maloney that failed under the previous council over the summer, passed unanimously.
This was a first step in a much-needed direction, according to Kris Krüg, executive director of BC + AI Ecosystem Association, who spoke in favour of the motion at council.
BC + AI is a grassroots nonprofit representing “AI builders” who are interested in having “deeper,” more nuanced conversations about AI’s future.
“The Silicon Valley way of rolling out AI is not the only way to do things,” Krüg told Vancity Lookout. “We need to regulate and set some parameters about what we’re willing to accept and on what terms so we can gain the benefit of all these innovations and advances in technology.”
More public consultation on the horizon
However, it is unclear whether a regulatory framework will be developed in time should City Council be called to decide on the rezoning application for 111 East 5th Ave. in Mount Pleasant.
A public question-and-answer period will commence on Dec. 2 and run through Dec. 15.
At that time, the public can ask questions about the project in anticipation of a possible rezoning of the property, which, according to the application, includes converting the existing below-grade parking to Bulk Data Storage uses, adding a restaurant space and removing parking requirements for the development.
“I don’t think we should process any applications until we’ve got a regulatory framework figured out,” Krüg added. “And the other side of that is, we do need to figure that out.”
While Maloney told Vancity Lookout that it is not council’s place to be "unquestionable cheerleaders for AI… nor an immovable naysayer,” it is council’s role to “make effective land use decisions about the AI data centre proposals that come before us.”
Her goal with this motion was to “give us as much control, transparency and accountability” as possible, she said. “I don’t want a situation where an AI data centre is constructed and then has far bigger external effects outside the boundary of the premises than was promised.”
While Maloney had initially pushed for a moratorium on approvals for AI data centre projects until the staff report could be completed, this was impeded by the Vancouver Charter, which requires the City to process rezoning applications.
Following the public question-and-answer period, council will have the option to vote on whether the rezoning application will go to a public hearing.
“The hope is that we don’t have a public hearing for a rezoning of a data centre until we’ve had that reporting back,” Maloney said. “But it may not work out that way.”
If a public hearing is scheduled before staff report back with a framework for the AI data centres, council will “just have to make a decision,” Maloney said.
Council does have the discretion to determine if a rezoning application will proceed to public hearings and has “broad powers to approve or not approve these applications.”
Although the area is currently zoned appropriately for an AI data centre, the rejection of the rezoning application could, in theory, halt the Mount Pleasant project.
However, senior levels of government do have broad powers to intervene and push the project ahead should it come to that, Maloney added.
TELUS leaves Westbank Vancouver AI data centre projects
As first reported in Daily Hive, TELUS has backed out as a major partner in the two AI data centre projects planned for Vancouver. Westbank has confirmed it intends to move forward with a different partner, which has yet to be publicly announced.
A TELUS spokesperson said in a written statement to Vancity Lookout that it “has decided not to proceed with co-developing two previously announced Vancouver data centres with Westbank.”
When asked why the telecommunications company decided to leave the projects and whether it was in response to public pressure, it did not directly address the question.
However, a TELUS spokesperson noted that as part of a federal initiative, the company is “actively expanding our Kamloops facility to 20 [megawatts] by the end of 2028.”
They added that they will have more to share about their strategy in the coming months.
A Westbank spokesperson said in a written statement to Vancity Lookout that “we can confirm the two proposed compute facilities in Vancouver are moving forward, and that the conclusion of our partnership with TELUS was a mutual decision.”
Maloney speculated that their departure from the project could have been related to “reputational risk” in the wake of several protests against the data centres.
Anna Busch, an organizer with No AI Vancouver, told Vancity Lookout that the group considers TELUS’ withdrawal from the project “a win.”
“The public has really stepped forward to say ‘we don’t want this in our town,’” said Busch. “Any delay can cause a financial slowdown for these companies.”
Krüg added that “as the details of the deal change, that allows us to [have some] breathing room and put processes in place with teeth, like audits, third-party site evaluations, targets, and true public benefit.”
Considerations as projects move into next steps
The debate over what place, if any, large-scale AI data centres should have in the future of our city – or even our country – continues to be deeply polarizing.
A Westbank representative wrote to Vancity Lookout that “this kind of infrastructure should be held to a high standard, and we think ours can help show what that looks like,” noting that their facilities will be smaller scale, running on “clean hydroelectricity” with reduced water consumption and waste heat going into Vancouver’s district energy systems.
But some critics are not convinced. “I just don’t see a way that it can be done that is not harmful,” said Busch. “We’re in a climate disaster, and it feels mind-boggling that we’re considering putting these centres everywhere.”
As a Mount Pleasant resident, Busch said she hopes to see sufficient delays in the project for further research to emerge that clearly demonstrates the negative human health effects of proximity to these centres.
In reference to the polarizing nature of AI-related discussions, Krüg noted that “for sure it’s a middle path.” He acknowledges that two things can be true at once: In short, AI can be both an incredibly destructive and creative force.
“There’s not a utopian future where no businesses in British Columbia use artificial intelligence in their operations. We’re way past that at this point,” he said, highlighting the importance of Vancouver for creative industries, like video game studios and the film industry, that rely on AI.
While he’s not in support of the Westbank data centres, he added “if we want to continue to have [creative] businesses operating here, we need to find a way to give them the tokens they need … just in a clean, green and just way that reflects our values.”
Westbank said in a written statement that they “support the City’s review of data centres and direction to develop policy for them… as part of our rezoning conditions we’re commissioning an independent study to measure those impacts and we’ll share the results.”
Should these projects ultimately go forward, Busch said she hopes to see Westbank be transparent with the public. “They need to give people an opportunity to react. If they do pass, they’re going to be part of our community… and we are the community members.”
Copyright 2026, Vancity Lookout. All rights reserved.
Maddi Dellplain, Local Journalism Initiative Reporter, Vancity Lookout.