Nunavut air base being built last because threat from Russia comes from the west: colonel

Construction in Iqaluit is due to start by 2029 and finish by 2040, with no permanent military presence.
Nunavut air base being built last because threat from Russia comes from the west: colonel
From left, Col. Patrick Dube and Christian Middleton, project manager of the Iqaluit base for the Department of National Defence, ahead of the Nov. 26 public engagement session about the Iqaluit air base to be constructed by 2040. (William Koblensky Varela/NNSL photo)
Writer

Iqaluit’s air base is the last of four forward operating locations being constructed in the North by the Department of National Defence because Canada is more exposed to attacks from Russia in the Western Arctic.

Less existing infrastructure in the territorial capital also put the construction date at the bottom of the list, explained Col. Patrick Dube, director of the North American Aerospace Defense Command (NORAD) Northern Basing Infrastructure.

“There’s just a higher threat to Canada from the western flanks. So we have a higher priority to build the infrastructure on the west side, and we have existing infrastructure in the east — it’s a bit more developed, like in Goose Bay,” Dube said.

That existing infrastructure in Goose Bay, N.L. moved it up on the construction schedule.

The Department of National Defence is building four air force forward operating locations in the North, starting in Inuvik, then in Goose Bay, N.L., before constructing a base in Yellowknife, leaving Iqaluit as the last base to begin construction.

Construction is due to start in Iqaluit by 2029 and finish by 2040, with the entire project costing $5 billion.

“We’re more exposed in the west than in the east. In the east you have Greenland, you have Northern Europe, so we’re a bit less exposed,” Dube said.

Start dates for construction on the air bases are being spread out among the four locations to avoid overwhelming developers and take lessons learned from one base’s construction to the next.

There will be no permanent presence of Canadian Armed Forces members in Iqaluit following the base’s completion in 2040.

“Canadian Armed Forces members here will deploy, conduct their operations, and then redeploy south to their main operating bases,” Dube said.

Improved sewage and drinking water treatment systems for the City of Iqaluit and fire hall upgrades are expected as part of the community investment in association with the air base, explained Christian Middleton, project director at the Department of National Defence.

A multi-purpose building for disaster response or search and rescue with offices and two garages is also part of the planned perks for Iqaluit.

Road maintenance or other community benefits from the forward operating location have not been decided.

“It’s something that we are considering, but that one’s a little more complicated because we would have to be able to attribute the defence need and the defence impact on the road system, and we don’t have enough information for that,” Middleton explained.

Consultations with Nunavut Tunngavik Inc., the Qikiqtani Inuit Association, and the Amaruq Hunters & Trappers Association have already begun this week and are expected to continue until construction is completed by 2040, Middleton explained.

The air base has an Inuit impact benefit plan to ensure some of the $5 billion in construction costs goes to Nunavummiut.

“Whatever opportunities that we have, we can try and make it so that as many Inuit businesses as possible can compete for those opportunities,” Middleton said.

Nearly 17 per cent of federal contracts in the Northwest Territories and Nunavut went to Indigenous businesses in 2023-2024, and the federal government has a minimum threshold of five per cent Indigenous-owned contractors for all of its projects Canada-wide.

A request for proposals is expected to be issued in January 2028, and the percentage of Inuit-owned businesses engaged as contractors for the Iqaluit air base will be known by 2030 or 2031.

Maximizing the contract opportunities for Inuit-owned businesses is Middleton’s aim, but the actual number is not yet known.

“I don’t have that answer yet, but it’s going to be, I’d say, a reasonably high number,” he said, adding that the number will likely fluctuate year to year.

A $5-billion price tag for construction exceeds Nunavut’s entire industrial capacity, according to information passed on to Middleton, and that means any business that wants to compete for a contract will have a decent shot.

“One of the initial things we’re going to have to do is to clear the ground, which in our case is going to involve a lot of blasting and rock removal, and then a lot of light foundation work and so forth, and a lot of that could be done with general labour and heavy equipment,” he said. “So there’s probably a lot more opportunity for local businesses to get a piece of that than, say, contributing to the construction of a high-security operations centre.”

Currently, the air force base at the Iqaluit airport has six fighter jet bays and a small garage.

The future base will be built beside the Iqaluit Airport, where the hangars are currently located.

A longer runway, ammunition storage, fuelling stations, hangars, operation centres and warehouses are part of the draft plan.

Copyright 2026, Nunavut News. All rights reserved.

William Koblensky Varela, Local Journalism Initiative Reporter, Nunavut News.

Poilievre says nurse may lose job after photo with him at Wainwright

Poilievre says nurse's job threatened over photo

11 Government of Canada jobs you can get in these cities that pay up to $120,000 a year

CSIS is hiring for jobs in admin, IT, software development, and other work areas.